ROUNDUP · PUBLISHED · UPDATED · SOURCES CHECKED OCT 17, 2026
AI construction scheduling in 2026: ALICE, nPlan, Karmen, SmartPM, Outbuild, Planera, Foresight, Nodes & Links, and Nialli
“AI scheduling” now covers several different jobs: simulating alternative ways to build, drafting a schedule from project documents, forecasting delay risk from historical schedules, auditing or asking questions of the schedule you already have, and digital pull planning for the Last Planner System. We re-read these vendors' public pages through Oct 17, 2026 and sorted them by the job each one says it does. Vendor statements are claims; nothing below is a test result or a recommendation, and prices appear only where the vendor publishes them.
On this page
Several different jobs under one label
Our framing, not a vendor claim: before comparing tools, decide which job you are buying for. ALICE describes scenario simulation and optimization. Karmen describes drafting and editing schedules from drawings and specs. nPlan and Foresight describe risk forecasting and completion prediction on existing schedules (from different training bases). SmartPM describes automated analytics on the CPM schedules you already maintain. Nodes & Links describes asking the schedule questions with auditable answers. Outbuild and Planera are scheduling platforms in their own right that describe built-in AI. Nialli is digital pull planning built on the Last Planner System, not a CPM replacement. Several of these overlap at the edges, so read each vendor's own description below.
Simulate and optimize: ALICE
ALICE describes itself as AI-powered generative construction scheduling software that automates ‘what-if’ scenario exploration; its homepage says it rapidly simulates millions of possible construction scenarios to find the most efficient plan (vendor claim). It lists ALICE Optimize (works with an existing Primavera P6 or Microsoft Project schedule), ALICE Analyze (schedule, project, and portfolio analytics), ALICE Model (a baseline from a 3D model), ALICE FieldPlan (in beta, field plans from drawings), and a Schedule Insights Agent for chatting with a schedule. ALICE says you can import schedules from Microsoft Project, Oracle Primavera P6, or Oracle Primavera Cloud.
ALICE says it has been deployed on more than $410 billion of construction projects and cites 17% shorter project duration, 14% labor cost savings, and 12% equipment cost savings (vendor claims, not verified; the page does not describe how they were measured). It lists project types from data centers and energy plants to railways, highways, bridges, and tunnels, and says the platform is SOC 2 Type II compliant and Cyber Essentials Plus certified.
Pricing: not publicly listed. ALICE's pricing page offers a custom quote based on the size and scope of your projects, lists unlimited users and unlimited data, and says ALICE is most often used by GCs and owners on projects with a construction value of at least $75M.
Draft from documents: Karmen
Karmen calls itself an AI scheduling co-pilot. It says it reads project documents (drawings and specs as PDF, historic schedules and templates from P6, MSP, or XER), and can then be steered in natural language to build a WBS, activities, and logic links from scratch, update existing schedules including time-impact analysis with structured fragnets, and track float and critical-path movement between monthly updates. It exports to Primavera P6 and Microsoft Project.
Karmen says it reads thousands of pages of specs and drawings in minutes and learns from your historic schedules to sequence work the way you would (vendor claims, not verified). On security it says SOC 2 reports are shared on request, data is encrypted in transit and at rest, and project documents are never used to train shared models. Pricing: not publicly listed; the site routes to a demo booking.
Forecast risk from history: nPlan
nPlan describes AI for project controls and delivery trained on a dataset of 750,000 historical schedules representing over $2Tn of construction spend, and says its AI has $500bn of projects under active management (vendor claims). It says it works with your existing schedules and describes four uses: generating and editing schedules from scope documents, forecasting the uncertainty of every activity, flagging risky activities and checking them against an uploaded risk register, and project and portfolio summaries. A blog post featured on its homepage says Schedule Studio now connects to Claude and ChatGPT for questions, edits, health checks, and exporting an updated XER.
nPlan's homepage also points to a Model Performance 101 white paper that frames forecast accuracy as mean absolute error (MAE). Pricing: not publicly listed; we found no pricing page (nplan.io/pricing returned a 404 on Oct 17, 2026).
Predictive delivery and QSRA: Foresight
Foresight describes a London-based predictive project delivery platform that turns existing construction schedules into executive reporting, schedule-quality and change tracking, risk assessment, completion forecasting and portfolio assurance. Its risk page lists Quantitative Schedule Risk Analysis (QSRA), a Criticality Score and risk density, run-rate and resource analysis, and an always-updated risk register. Its completion-forecasting page says models are trained on over 1 million real-world construction activities, predicts best-case, worst-case and most-likely finish dates, generates Completion Plans that tag activities as Blocking, Delaying, On Schedule or Completed, and supports what-if simulation of scope, sequencing or resource changes.
The homepage claims 2x more accurate forecasts than bottom-up schedules, a 30% reduction in overruns and 40+ hours saved per month on reporting (vendor claims, not verified; no measurement method on the pages we read). A banner announces a $25M Series A led by Macquarie Capital Venture Capital (company statement). Sectors highlighted include data centers and government. Pricing: not publicly listed; the site routes to Talk to our team (/pricing not found on Oct 17, 2026). Our Foresight vs nPlan compare sets the two forecasting platforms side by side.
Ask the schedule: Nodes & Links
Nodes & Links describes an AI decision-intelligence platform for capital-project controls. In its AI Mode, users ask plain-language questions about one project, two schedule versions or a whole portfolio; it says every answer runs through its project-controls models and shows its reasoning steps and sources. Listed models include Integrity (the 14 DCMA checks plus proprietary checks), Change Control between schedule versions, Delay Navigator, earned value, QSRA and QCRA, and automated workflows can re-check each new schedule version and email the results.
Its integrations sync schedule versions plus documents, RFIs, change orders and cost, and a Platform Mode offers the same modules with or without AI. It states ISO 27001 certification and that integrated content is never used to train AI or LLM models (vendor claims). Pricing: not publicly listed; /pricing redirects to the homepage, which offers Book a demo. Our Nodes & Links vs Foresight compare covers the two AI project-controls platforms.
Audit the schedule you have: SmartPM
SmartPM describes a project controls and schedule analytics platform that integrates with your existing CPM scheduling software and provides what it calls Automated Project Controls: schedule quality checks, progress against baselines, delay and compression metrics, a web-based Gantt, and company and executive dashboards, aimed at GCs, owners, and developers in commercial construction. Neither its homepage nor its pricing page describes the product as AI, which is why our directory tags it Not AI-first; it is included here because buyers often evaluate it alongside AI scheduling tools.
SmartPM is one of the few vendors in this group that publishes full prices. Its pricing page lists Essentials at $12K per year for up to 50 projects and Controls at $25K per year with 5 Controls slots, both with unlimited users; Controls adds what-if scenarios and time impact analysis, portfolio insights, and dedicated onboarding. The page also offers a 60-day risk-free trial.
Scheduling platforms with built-in AI: Outbuild and Planera
Outbuild calls itself the first fully integrated, AI-powered, collaborative scheduling and field coordination platform built for construction (vendor claim) and markets “AI agents for scheduling, built on construction logic.” It connects the master schedule to lookaheads and weekly work plans, and its pricing FAQ says it can replace P6, MS Project, and Excel, exports to PDF, XML, or XER, and integrates two-way with Procore and with Autodesk Construction Cloud. Outbuild says it starts at $999 per month billed annually, priced by annual construction volume rather than by user or project, with unlimited users and projects; its Pro tier is custom-priced.
Planera describes AI-native CPM scheduling: critical path and float management, DCMA-14 quality checks, resource loading, field schedules tied to the master, and an AI assistant it calls manny that turns plain-English requests into schedules and updates, explores what-if scenarios, flags missing logic and shrinking float, and drafts owner updates and delay narratives. Its pricing page describes customized pricing with unlimited users; prices are not publicly listed.
Digital pull planning: Nialli
Nialli Visual Planner is construction planning software built on the Last Planner System for digital pull planning. It is a different job from the CPM tools above: color-coded trade lanes, drag-and-drop activities and touch displays for trailer and office planning boards, not generative CPM optimization. The homepage says milestones and activities can be imported from Oracle Primavera P6, Asta Powerproject or Microsoft Project; Percent Plan Complete (PPC) and reasons-for-variance data generate as teams status tasks; constraints show as warning dots on affected tasks; up to three connected touch displays can share one plan; and remote users join from a laptop, tablet or phone.
Pricing is public: Single-plan subscription $1,400 per year (USD), flat price with unlimited users, core features and basic support (one plan supports up to 25 lanes of activity); Multiplan subscription with volume pricing on request; 30-day free trial, no credit card (pricing page, Oct 17, 2026). Our directory tags it Not AI-first.
BlackHyve, tagged AI features added to an established product in our directory (its pages describe AI voice-note transcription and an assistant called Barry), records the same question from the trade contractor's side: its pages describe production management that sets work installed against the estimate and logs "drift", the broken conditions such as access, materials, information or sequence that slow a crew, with foremen capturing events by voice or video and external drift routed to notices, change orders and claims. It publishes no prices. Nialli's support pages say a Not done activity requires a reason for variance; see our Nialli vs BlackHyve comparison for how the two records differ.
Next to the schedule: preconstruction management (Join)
Not every preconstruction tool in this area is a scheduler, or AI-first. Join, which our directory files under precon management and labels Not AI-first, describes preconstruction and design-phase management software: cost trending of the budget, estimates, contingencies and allowances as design progresses, stakeholder decision tracking, design management, and procurement coordination, for general contractors, owners, design teams and trades. Re-read Oct 17, 2026, Join's homepage now calls it a unified system of record for preconstruction and the design phase that ties real-time cost and schedule data to design evolution, with scenario modeling and risk and contingency governance, built for Design-Build, CMAR, IPD, IFOA and TVD delivery; it says it uses AI-enabled workflows but does not detail them, so we keep the Not AI-first label. Pricing: not publicly listed; Join's pricing page offers tailored pricing and a customized quote, with no prices shown (vendor page, Oct 19, 2026; the fast-track option it listed earlier is no longer on the page). It is a different job from the scheduling tools above: tracking cost and decisions during design rather than building or analyzing the CPM schedule. Re-read Oct 18, 2026, Join's FAQ says it does not replace estimating software (it imports Sage, WinEst and Destini files), and its Agents page describes connecting your own AI tools through an MCP server and API. Our Join vs BidLight compare sets its cost trending beside BidLight's model-based cost in Revit.
What to ask before a pilot
These are our suggestions, not findings. Run every tool on the same closed project you already know well, so you can judge its output against what actually happened. For tools that draft schedules (Karmen, nPlan's generative features, Planera, ALICE Model), ask how many hours a scheduler needed to turn the draft into a submittable baseline, and check logic density and open ends. For tools that forecast or score (nPlan, Foresight, SmartPM, ALICE Analyze), ask what the forecast or score was on past projects versus actual completion. For Nodes & Links, ask whether answers cite the schedule version and change that produced them. For Nialli, ask how PPC and constraint logs feed back into the CPM. And confirm the round trip: whether the tool reads and writes your P6 or MS Project files without losing codes, calendars, or resource loading. Our scheduling pilot guide lists the full question set.
Takeaways
- Pick the job first: simulate options, draft from documents, forecast risk, ask the schedule, audit an existing CPM, run a scheduling platform, or do digital pull planning.
- Published starting prices in this group: SmartPM, Outbuild and Nialli; ALICE, nPlan, Karmen, Planera, Foresight and Nodes & Links quote on request.
- Duration, accuracy and cost-saving percentages on vendor homepages are claims without a published method on the pages we read.
- Test on a closed project you know, and check the P6/MS Project round trip before you trust the output.
Questions and answers
From the desk research above (vendor pages read Oct 17, 2026). Vendor statements are claims from vendor sites.
What does AI construction scheduling software do?
Several different jobs, by vendor description: simulating alternative ways to build (ALICE), drafting a schedule from drawings and specs (Karmen), forecasting delay risk and completion from existing schedules (nPlan, Foresight), auditing the CPM schedule you already have (SmartPM, which our directory tags Not AI-first), asking the schedule questions with auditable answers (Nodes & Links), scheduling platforms with built-in AI (Outbuild, Planera) and digital pull planning (Nialli). Our information on them comes from vendor websites (desk research).
Which AI scheduling tools publish their prices?
In this group, SmartPM, Outbuild and Nialli. SmartPM lists Essentials at $12K per year for up to 50 projects and Controls at $25K per year, both with unlimited users; Outbuild says it starts at $999 per month billed annually, priced by annual construction volume; Nialli lists a single-plan subscription at $1,400 per year with unlimited users. ALICE, nPlan, Karmen, Planera, Foresight and Nodes & Links quote on request.
Do AI scheduling tools work with Primavera P6 and Microsoft Project?
Several say so: ALICE Optimize works with an existing Primavera P6 or Microsoft Project schedule; Outbuild's pricing FAQ says it can replace P6, MS Project and Excel and exports to PDF, XML or XER; Nialli imports milestones and activities from Oracle Primavera P6, Asta Powerproject or Microsoft Project; SmartPM integrates with your existing CPM scheduling software. Our suggestion: check the round trip on your own files, including codes, calendars and resource loading.
Are AI schedule forecasting accuracy claims verified?
Not on the pages we read. Duration and accuracy percentages on vendor homepages are vendor claims without a published measurement method. Our suggestion: for tools that forecast or score (nPlan, Foresight, SmartPM, ALICE Analyze), ask what the forecast or score was on past projects versus actual completion, and run every tool on the same closed project you already know well.
What is digital pull planning, and is it AI?
Nialli Visual Planner is digital pull planning built on the Last Planner System: color-coded trade lanes, drag-and-drop activities and touch displays for planning boards, with Percent Plan Complete (PPC) and reasons-for-variance data generated as teams status tasks. It is a different job from CPM scheduling, and our directory tags it Not AI-first. It lists a single-plan subscription at $1,400 per year and a 30-day free trial.
Newsletter
The monthly roundup
One email a month: new construction AI tools, price changes, and what estimators are saying. No spam, unsubscribe anytime.
Sign-ups are handled by beehiiv and confirmed by email. See privacy.
Sources (20)
- ALICE Technologies homepage https://www.alicetechnologies.com
- ALICE pricing https://www.alicetechnologies.com/pricing
- nPlan homepage https://www.nplan.io
- Karmen homepage https://www.karmenai.com
- SmartPM homepage https://smartpm.com
- SmartPM pricing https://smartpm.com/pricing
- Outbuild homepage https://www.outbuild.com
- Outbuild pricing https://www.outbuild.com/pricing
- Planera homepage https://www.planera.io
- Planera pricing https://www.planera.io/pricing
- Foresight homepage https://www.foresight.works/
- Foresight risk assessment https://www.foresight.works/platform/risk-assessment
- Foresight completion forecasting https://www.foresight.works/platform/completion-forecasting
- Nodes & Links homepage https://nodeslinks.com
- Nialli homepage https://www.nialli.com/
- Nialli pricing https://www.nialli.com/pricing
- Nialli: PPC and reasons for variance reporting https://www.nialli.com/support/ppc-and-reasons-for-variance
- BlackHyve: what is drift https://www.blackhyve.com/drift.html
- Join homepage https://join.build
- Join pricing https://join.build/pricing/
All sources accessed Oct 17, 2026.
Tools in this article (alphabetical, not ranked)
- ALICE · Scheduling
- BlackHyve · Project drift tracking
- Buildots · Progress tracking
- cmBuilder · Visual site & logistics planning
- Foresight · Predictive schedule analytics & delay risk
- Join · Preconstruction management
- Karmen · AI scheduling co-pilot
- Nialli · Digital pull planning
- Nodes & Links · AI project controls & schedule analysis
- nPlan · Scheduling & risk
- Outbuild · Collaborative scheduling & lookahead
- Planera · AI-native CPM scheduling
- SmartPM · Schedule analytics & project controls
Side-by-side comparisons
- Karmen vs cmBuilder
- cmBuilder vs Planera
- BlackHyve vs ALICE
- Planera vs PLOT
- Outbuild vs PLOT
- Nialli vs PLOT
- Karmen vs Piper AI
- Foresight vs Piper AI
- nPlan vs BlackHyve
- Join vs Piper
- Foresight vs BlackHyve
- Planera vs BlackHyve
- Nialli vs SmartPM
- Outbuild vs cmBuilder
- Nialli vs nPlan
- Karmen vs BlackHyve
- Outbuild vs BlackHyve
- Ontollo vs Nodes & Links
- Nialli vs cmBuilder
- Buildots vs Foresight
- ALICE vs Nialli
- BlackHyve vs SmartPM
- Nialli vs Karmen
- cmBuilder vs ALICE
- Outbuild vs Nodes & Links
- Nialli vs Nodes & Links
- Foresight vs Planera
- Steelray Delay Analyzer vs Planera
- Planera vs Nodes & Links
- Outbuild vs Foresight
- Nodes & Links vs ALICE
- Nodes & Links vs BlackHyve
- SmartPM vs Buildots
- Karmen vs Steelray Delay Analyzer
- Karmen vs Foresight
- Planera vs nPlan
- Buildots vs nPlan
- ALICE vs Foresight
- Karmen vs Outbuild
- ALICE vs Planera
- Outbuild vs nPlan
- ALICE vs SmartPM
- Karmen vs nPlan
- Karmen vs SmartPM: AI schedule building or schedule analytics
- Karmen vs Nodes & Links
- Join vs ConCntric
- Nodes & Links vs SmartPM
- ALICE vs Outbuild
- nPlan vs Nodes & Links
- Foresight vs SmartPM
- BlackHyve vs blade ai
- Steelray Delay Analyzer vs Nodes & Links
- Assignar vs Bridgit
- Planera vs SmartPM
- Nialli vs Outbuild
- ALICE vs nPlan
- ALICE vs Karmen
- nPlan vs SmartPM
- Outbuild vs Planera
- Karmen vs Planera
- Foresight vs nPlan
- Nodes & Links vs Foresight
- Nialli vs BlackHyve
- Join vs BidLight
- Nialli vs Planera
Related articles
- Construction AI funding, mid-September to mid-October 2026: back office, design review, and autonomy Funding brief · 2026-10-15